Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberMEC19-04242
StatusFinaled
Name RM MECHANICAL
Site Address 5015 N PIERCE PARK LN
Project Name 
Customer NumberD19-013
ePlanReviewNo
Description
New: Dry Mechanical Scope:
Provide and install 31ea Water Source Heat Pumps with associated ductwork and controls
Provide and install 3ea Rooftop Units with associated ductwork and controls
Provide and install 2ea Energy Recovery Units with associated ductw
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final5/11/20205/11/20205/11/2020PPASS
DetailsBen Livingston
Final5/1/20205/4/20205/4/2020PPART
DetailsBen Livingston
Contact person is Shawn Hicks, Phone Number: ###-#### Phone #: ###-#### Inspection requested via web by RM Mechanical
- equipment needs tobe under class 1 hoods by 6" min.
Rough-in3/20/20203/23/20203/23/2020PPASS
DetailsBen Livingston
Rough-in for cover
Music Rm, Cafeteria and Dry Storage Area C

3/23/20,PM Shawn Hicks ###-####
Phone #: ###-#### Inspection requested via web by RM Mechanical
-
Music Rm, Cafeteria and Dry Storage Area C


above grid ok-
Rough-in3/3/20203/4/20203/4/2020APASS
DetailsBrian Scoles
Rough-in for cover, 2nd layer grease duct, dishwasher hood, Admin Area B1 Phone #: ###-#### Inspection requested via web by RM Mechanical- 2nd layer firewrap ok from hoods thru curb- MAU insulation all drops in kitchen and duct work ok- kitchen diffusers, flex and insulation ok- missing insulation in storage room supply duct above hard lid- dishwasher exhaust duct and seal ok
Rough-in2/26/20202/27/20202/27/2020APASS
DetailsBen Livingston
rough-in, MAU in kitchen
Shawn Hicks ###-#### Phone #: ###-#### Inspection requested via web by RM Mechanical
- mau duct seal okay -
Rough-in2/21/20202/21/20202/21/2020PPASS
DetailsBen Livingston
Grease Duct 1st layer fire wrap inspection

Pierce Park Elem. D19-039

2/21/20 PM

Shawn Hicks ###-####
Phone #: ###-#### Inspection requested via web by RM Mechanical
- 1st layer fire wrap okay -
Rough-in2/19/20202/20/20202/20/2020PPASS
DetailsBen Livingston
Rough-in Inspection: Cafeteria Grease duct light inspection, Area C hard lids, Rm. 276 for cover, Area B1 ; B2 classrooms for cover
Shawn Hicks ###-####

Aaron Roberts ###-####
Phone #: ###-#### Inspection requested via web by RM Mechanical
- light test on reconnect to hood -
- area c hard lids -
- 1st and 2nd floor class rooms above grid okay -
Rough-in2/7/20202/10/20202/10/2020PPASS
DetailsBen Livingston
Rough-in inspection, Area B, 2nd floor hard ceilings

Shawn Hicks is site contact ###-#### Aaron Roberts ###-####
Phone #: ###-#### Inspection requested via web by RM Mechanical
- 2nd floor B above hard lids okay -
Rough-in1/22/20201/23/20201/23/2020APART
DetailsBen Livingston
Area B1 Hardlid inspection site contact is Shawn Hicks ###-#### or Aaron Roberts ###-#### Phone #: ###-#### Inspection requested via web by RM Mechanical
-above hard lids in Area 1B okay -
- fire wrap on greese duct needs to extent above roof line in curb -
Rough-in1/16/20201/17/20201/17/2020PPASS
DetailsBen Livingston
Rough Overhead tile inspection on Area A Phone #: ###-#### Inspection requested via web by RM Mechanical
- area A 1st and 2nd floor above grid okay -
Rough-in1/13/20201/14/20201/14/2020PPASS
DetailsBen Livingston
1st Layer Grease Duct
###-####
Phone #: ###-#### Inspection requested via web by RM Mechanical
- first layer fire wrap okay-
Rough-in1/6/20201/7/20201/7/2020APASS
DetailsBen Livingston
Mechanical Rough-in inspection for cover, hard lid Area A2 Site Contacts are Aaron Roberts ###-#### and Shawn Hicks ###-#### Phone #: ###-#### Inspection requested via web by RM Mechanical
- area A2 hard lids okay -
Rough-in12/18/201912/20/201912/20/2019APASS
DetailsBen Livingston
Rough-in inspection, grease duct light test Phone #: ###-#### Inspection requested via web by RM Mechanical
- grease duct light test from roof to wye okay -
- area A hard lids and electric heater -
Rough-in11/8/201911/12/201911/12/2019APASS
DetailsBen Livingston
D19-013 Rough-in inspection, Area A ; B, 2nd Floor Aaron Roberts, ###-#### Phone #: ###-#### Inspection requested via web by RM Mechanical
- 2nd floor area A,B duct seal -
Rough-in10/4/201910/7/201910/7/2019PPASS
DetailsBen Livingston
rough in pm : Aaron Roberts, ###-#### Phone #: ###-#### Inspection requested via web by RM Mechanical
- duct seal area B -
Rough-in9/24/20199/25/20199/25/2019APASS
DetailsBen Livingston
Mechanical Rough-in inspection (Duct seal)
Aaron Roberts ###-#### Phone #: ###-#### Inspection requested via web by RM Mechanical
- duct seal area A -