Final | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | PASS |
Jack Reynolds
|
|
|
Final Inspection - Please contact Robbie prior to arrival - ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - final ok
|
Final | 3/6/2020 | 3/9/2020 | 3/9/2020 | P | FAIL |
Jack Reynolds
|
|
|
Final Inspection - Please contact Robbie prior to arrival - ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - duct blast energy sticker needs information filled out completely
|
Rough-in | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | PASS |
Jack Reynolds
|
|
|
Request cover inspection. Please contact Robbie at ###-#### prior to arrival. Phone #: ###-#### Inspection requested via web by Commercial Coordinator - R/I ok - small amount of return duct and fresh air connection is exposed in garage can be seen at later date
|
Rough-in | 11/26/2019 | 12/2/2019 | 12/2/2019 | A | PART |
Jack Reynolds
|
|
|
Inspection requested for 12/2. Please contact Mark prior to coming out to the site. ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - partial R/I ok to cover everything but soffits for range and fresh air ducts in garage. Schedule inspection when ready for complete R/I
|