Final | 1/24/2020 | 1/27/2020 | 1/27/2020 | A | PASS |
Brian Scoles
|
|
|
A/c changed out. from 3 ton to 3.5 ton Phone #: ###-#### Inspection requested via web by Oleg Chervak- final ok
|
Final | 1/23/2020 | 1/24/2020 | 1/24/2020 | A | FAIL |
Brian Scoles
|
|
|
Corrections made please respect Gc 0425 or 3484 Phone #: ###-#### Inspection requested via web by Oleg Chervak- condenser does not match man j
|
Final | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | FAIL |
Brian Scoles
|
|
|
MEC AND FIREPL Phone #: ###-#### Inspection requested via web by Oleg Chervak 1- need duct blast test completed 2- need air balance report onsite 3- need man j onsite 4- need to seal line set at ac /c where penetrates crawl vent 5- missing 2 supply registers 2nd floor
|
Rough-in | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | PASS |
Brian Scoles
|
|
|
Correction made please reinspect Phone #: ###-#### Inspection requested via web by Oleg Chervak- R/I hvac and fireplace ok
|
Pressure Test | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | PASS |
Brian Scoles
|
|
|
Correction made please reinspect Phone #: ###-#### Inspection requested via web by Oleg Chervak- 20lb gas pass tagged meter location- 5lb flue pass
|
Rough-in | 11/15/2019 | 11/18/2019 | 11/18/2019 | A | FAIL |
Brian Scoles
|
|
|
MEC AND FIREPL Phone #: ###-#### Inspection requested via web by Oleg Chervak- 1- gas gauge under 20psi 2- need flue test completed- 3- insulation shield needs 1" clearance need 7" pipe not 6" and remove combustible material at roof touching pipe 4- bare metal wye branches in crawl need insuluated and flex duct supported off ground all areas where in contact
left notice front window
|
Pressure Test | 11/15/2019 | 11/18/2019 | 11/18/2019 | A | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- gas gauge under 20psi- need flue under test
|