Final | 12/13/2019 | 12/16/2019 | 12/16/2019 | A | PASS |
Brian Scoles
|
|
|
Copy of air balance report will be onsite. Phone #: ###-#### Inspection requested via web by Stephen Lee- final ok- airbalance on hood ok- clearances on equipment ok- card signed
|
Rough-in | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | PASS |
Brian Scoles
|
|
|
Inspection of two layers of exhaust hood wrap. Photos will be emailed or texted from John Hall (###-####). Phone #: ###-#### Inspection requested via web by Stephen Lee- 2nd layer firewrap ok- need engineer approval from converting from round duct to square duct thats installed
|
Rough-in | 11/21/2019 | 11/25/2019 | 11/25/2019 | A | PASS |
Brian Scoles
|
|
|
Secondary light test of grease duct after installation on jobsite. Phone #: ###-#### Inspection requested via web by Stephen Lee- light test pass ok for firewrap
|
Rough-in | 11/20/2019 | 11/21/2019 | 11/22/2019 | A | PASS |
Brian Scoles
|
|
|
Scheduling a grease duct light test to be administered at our shop. Address as follows: 1776 Commerce Ave, Boise 83705 Phone #: ###-#### Inspection requested via web by Stephen Lee- light test on drop with transition 6 feet and offset 8 feet at shop ok
|