Rough-in | 8/10/2020 | 8/10/2020 | 8/10/2020 | P | PASS |
Ben Livingston
|
|
|
cover in bathrooms on 3rd floor through 9th floor Phone #: ###-#### Inspection requested via web by Amanda Farnsworth -4th and 5th floor restrooms okay
|
Rough-in | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PART |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Amanda Farnsworth - Okay to insulate ductwork in 2nd floor shaft. need to remove sheetrock to be able to inspect fire/smoke damper framing. Need manufactures certification for repaired fire blanket on 4th floor
|
Rough-in | 7/13/2020 | 7/14/2020 | 7/14/2020 | A | PART |
Chad Schwendiman
|
|
|
It be for the shaft duct to be covered on floors 3-9 Phone #: ###-#### Inspection requested via web by Amanda Farnsworth - Okay to build shaft wall on floors 3, 5, 6, 7, 8 & 9. Need to repair or replace fire blanket on outside of the damper sleeve on 4th floor. If repaired need to provide the manufactures instruction for repairing when reinspected.
|
Rough-in | 5/22/2020 | 5/26/2020 | 5/26/2020 | A | PASS |
Chad Schwendiman
|
|
|
shaft duct inspected for insulation
Phone #: ###-#### Inspection requested via web by Amanda Farnsworth - Duct seal okay on shafts from 2nd floor through the 9th. floor
|
Rough-in | 8/13/2020 | 8/14/2020 | | P | |
Ben Livingston
|
|
|
3rd & 6th floor bathroom celing cover and 3rd floor-8th floor shaft wall cover
Phone #: ###-#### >> Inspection requested via web by Amanda Farnsworth
|