Final | 2/19/2020 | 2/19/2020 | 2/19/2020 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by JOSE DUARTE- final ok
|
Final | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | NR |
Brian Scoles
|
|
|
Garage code is 2468 Phone #: ###-#### Inspection requested via web by JOSE DUARTE- need air balance and duct blast completed- need approved man j onsite- need 90s degree installed on roof on intake for furnace per furnace manufacture 12 inchs minimum above roof
|
Rough-in | 12/30/2019 | 12/30/2019 | 12/30/2019 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by JOSE DUARTE- R/I ok
|
Pressure Test | 12/30/2019 | 12/30/2019 | 12/30/2019 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by JOSE DUARTE- 20lb gas pass tagged meter location- 5lb flue pass
|