Final | 5/11/2020 | 5/12/2020 | 5/12/2020 | A | PASS |
Brian Scoles
|
|
|
please call john prior to arrival for access Phone #: ###-#### Inspection requested via web by Nicholas Paige- final ok- no card onsite to sign GC trailer locked up
|
Card not on site to sign | 5/12/2020 | 5/12/2020 | 5/12/2020 | A | PASS |
Brian Scoles
|
|
|
please call john prior to arrival for access Phone #: ###-#### Inspection requested via web by Nicholas Paige- GC trailer lock up not onsite- no card to sign
|
Final | 4/20/2020 | 4/22/2020 | 4/22/2020 | A | PART |
Brian Scoles
|
|
|
please call John 30 min prior to arrival for access- ###-####
thanks Phone #: ###-#### Inspection requested via web by Nicholas Paige- condensate line on mini split ok- glue on floor multiple places could not get access to roof or other parts of building- GC will contact John when flooring completed to reschedule inspection- temp occupancy ok
|
Rough-in | 3/24/2020 | 3/25/2020 | 3/25/2020 | A | PASS |
Brian Scoles
|
|
|
rough in for cover. please call shawn prior to arrival for access Phone #: ###-#### Inspection requested via web by Nicholas Paige- R/I on flex registers and insulation all areas ok- ok for ceiling tiles
|
Rough-in | 2/6/2020 | 2/7/2020 | 2/7/2020 | A | PASS |
Brian Scoles
|
|
|
please call shawn 1 hr in advance so he can meet you onsite
thanks Phone #: ###-#### Inspection requested via web by Nicholas Paige- R/I ok- ok for grid all areas
|
Rough-in | 1/6/2020 | 1/7/2020 | 1/7/2020 | A | PART |
Jack Reynolds
|
|
|
please call Shawn prior to arrival for access. partial cover inspection for curbs. Phone #: ###-#### Inspection requested via web by Nicholas Paige - RTU curbs ok 4- hardlids R/I cover ok
|
Rough-in | 12/30/2019 | 12/31/2019 | 12/31/2019 | A | PART |
Brian Scoles
|
|
|
Please call Shawn Prior to arriving for access. this is a duct wrap inspection.
thanks, Phone #: ###-#### Inspection requested via web by Nicholas Paige- approved drawings onsite- seal on duct ok- ok for insulation- recall in inspection for full R/I when ready
|