Rough-in | 5/29/2020 | 6/1/2020 | 6/1/2020 | A | PASS |
Jack Reynolds
|
|
|
Phase 2 inspection. Fan shaft second layer of sheetrock and fire caulk Phone #: ###-#### Inspection requested via web by yuriy kryachun -units 240,241 2nd layer sheetrock and firecaulk ok to cover exhaust fan -units 330-341 2nd layer sheetrock and firecaulk ok to cover exhaust fan
|
Rough-in | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PART |
Jack Reynolds
|
|
|
Phase 2 seal and fire caulk inside of vent shaft. Inspection requested via web by yuriy kryachun - units 240,241 first layer sheetrock and fire caulk ok -units 330-341 first layer sheetrock and fire caulk ok
|
Rough-in | 5/9/2020 | 5/11/2020 | 5/11/2020 | A | PART |
Jack Reynolds
|
|
|
1st phase new part two last units on main floor and 12 units on the 3rd floor(floor above) Phone #: ###-#### Inspection requested via web by yuriy kryachun - units 240,241 exhaust duct R/I ok - unit 330- 341 exhaust duct R/I ok - ok for first layer sheetrock and fire caulk
|
Rough-in | 3/4/2020 | 3/5/2020 | 3/5/2020 | A | PART |
Jack Reynolds
|
|
|
Step 2 inspection. Second layer of sheetrock and fire caulk. Phone #: ###-#### Inspection requested via web by yuriy kryachun - 2nd layer and fire caulk ok on units 230-239 only - ok to cover exhaust fans
|
Rough-in | 3/4/2020 | 3/4/2020 | 3/4/2020 | A | PART |
Jack Reynolds
|
|
|
First step seal snd fire caulk the shaft Phone #: ###-#### Inspection requested via web by yuriy kryachun - inside layer and fire caulk ok for outside layer and fire caulk
|
Conference | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Jack Reynolds
|
|
|
Will be there at 8:30am Phone #: ###-#### Inspection requested via web by yuriy kryachun - Met mechanical contractor onsite to go over exhaust fan installation into subduct shaft. Need to see inside layer of sheetrock installed and fire caulked. Then will need to see outside layer of sheetrock installed and fire caulked before cover of exhaust fan is given. This was on units 230-239 - unit 217 exhaust fan correction is ok for cover
|
Rough-in | 3/1/2020 | 3/2/2020 | 3/2/2020 | P | FAIL |
Jack Reynolds
|
|
|
Units 230 thru 239 . ###-#### Yuriy Phone #: ###-#### Inspection requested via web by yuriy kryachun - need City approved plans onsite
|