Final | 2/28/2020 | 3/2/2020 | 3/2/2020 | A | PASS |
Jack Reynolds
|
|
|
The electrical was done by Sublime Electric. I called them to inform them that they needed to pull a permit. They told me that they''d have it pulled on Friday 02/28/20. Please check and pass our permit. Phone #: ###-#### Inspection requested via web by Arielle Hendricks - final ok
|
Final | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Arielle Hendricks - furnace ac coil co ok - need electrical contractor to pull electrical permit before mechanical permit final
|
Pressure Test | 2/20/2020 | 2/21/2020 | 2/21/2020 | P | PASS |
Jack Reynolds
|
|
|
Please call Blake on your way ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks - 20lb gas pressure test ok - tagged meter location - check gas pipe supports outside at final - I also talked with debest about pulling plumbing permit for their work
|