Final | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Chad Schwendiman
|
|
|
Building will be open, thanks Phone #: ###-#### Inspection requested via web by Gary Reeves
|
Final | 7/22/2020 | 7/23/2020 | 7/23/2020 | P | FAIL |
Brian Scoles
|
|
|
no access code door will be unlocked Phone #: ###-#### Inspection requested via web by Gary Reeves 1- condensate needs ran into floor drain 2- unit heater needs installed and roof flashing for b vent not installed correctly sitting on roof and needs sealed 3- need to remove grout around gas line penetration at meter and sealed weather tight 4- need to firecaulk penetrations into attic at furnace location IE OSA supply ducting and furnace intake and exhaust
left notice at plan location
|
Pressure Test | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | CANC |
Brian Scoles
|
|
|
Added gas line for a back up generator, Thanks Phone #: ###-#### Inspection requested via web by Gary Reeves- per phone call with Mike wrong address no backup generator at this address
|
Rough-in | 5/29/2020 | 6/1/2020 | 6/1/2020 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Reeves- R/I ok
|
Pressure Test | 5/21/2020 | 5/21/2020 | 5/21/2020 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Reeves- 20lb gas pass tagged meter location
|
Rough-in | 5/21/2020 | 5/21/2020 | 5/21/2020 | P | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Reeves- 1- all ducting needs finished with seal supply and R/A 2- note 4 shows 8" round fresh air and termination needs secured 3- all transfer air need to be installed per print with acoustial lining or get engineer approval for way installed/ supply duct no ran per print 4- need to remove insulation on supply duct branch lines to check seal 5- fix all rips and tears in arma flex and install nail plates 6- note 3 need combustion and flue ran to outside 7- note 5 need condensate ran 8- remove trim ring from unit heater b vent so clearances can be checked at ceiling 9- dryer vent ????
need to run per prints or get engineers approval in writing for the way ducting is installed and any deveation from approved prints
left notice front window roll up door
|