Final | 7/20/2020 | 7/21/2020 | 7/21/2020 | A | PASS |
Brian Scoles
|
|
|
FINAL Phone #: ###-#### Inspection requested via web by RM Mechanical- 60lb methane gas test pass- installed 3 shutoff valve to isolate main and for each boiler only- all piping stainless steel seal welded existing- final ok
|
Final | 7/17/2020 | 7/20/2020 | 7/20/2020 | P | CANC |
Brian Scoles
|
|
|
PRESSURE TEST Phone #: ###-#### >> Inspection requested via web by RM Mechanical Inspection cancelled from web by: RM Mechanical
|
Final | 7/16/2020 | 7/17/2020 | 7/17/2020 | A | CANC |
Brian Scoles
|
|
|
FINAL TEST PRESSURE FOR ADDED ISOLATION VALVES. Phone #: ###-#### Inspection requested via web by RM Mechanical- scheduled as conference
|
Conference | 7/17/2020 | 7/17/2020 | 7/17/2020 | P | DONE |
Brian Scoles
|
|
|
FINAL TEST PRESSURE FOR ADDED ISOLATION VALVES. Phone #: ###-#### Inspection requested via web by RM Mechanical- discussed pressure testing and locations
|