INSP - Final | 9/25/1995 | 9/26/1995 | 9/26/1995 | A | PASS |
Alan Hauser
|
|
|
09/25/95 350 - late as possible am FINAL
|
INSP - Final | 9/25/1995 | 9/26/1995 | 9/26/1995 | A | PASS |
Alan Hauser
|
|
|
09/25/95 350 - late as possible am FINAL
|
INSP - Framing/ Rough-in | 7/28/1995 | 7/28/1995 | 7/28/1995 | P | PASS |
Alan Hauser
|
|
|
r/i ok. 10 min
|
INSP - Gas pressure test | 7/28/1995 | 7/28/1995 | 7/28/1995 | P | PASS |
Alan Hauser
|
|
|
unions in gas line sealed with lock tight and pressure ok 20 min
|
INSP - Conference | 7/27/1995 | 7/27/1995 | 7/27/1995 | P | PASS |
Alan Hauser
|
|
|
called todds and talked to janet about sealing unions in the attic with lock tight. 20 min
|
INSP - Framing/ Rough-in | 7/27/1995 | 7/27/1995 | 7/27/1995 | P | PASS |
Alan Hauser
|
|
|
corrections made on flex in attic. still have corrections on gas piping. 20 min
|
INSP - Gas pressure test | 7/27/1995 | 7/27/1995 | 7/27/1995 | P | FAIL |
Alan Hauser
|
|
|
pipe size is ok, and pressure held but now they have added three unions in the attic. will accept if they seal them with lock tight. 15 min
|