INSP - Final | 10/9/1995 | 10/9/1995 | 10/9/1995 | | NR |
Alan Hauser
|
|
|
/ / 350 - COMB.-AIR OPENING NOT IN DOOR TO DRYER YET CHECK P.M. 10/10/
|
INSP - Clothes dryer | 10/2/1995 | 10/2/1995 | 10/2/1995 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED NEED COMB.-AIR AND MAKE-UP AI DRYER ROOM. CLEARANCE ON DRYER VENT IS OK, 2" REQUIRED.
|
INSP - Clothes dryer | 10/2/1995 | 10/2/1995 | 10/2/1995 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED NEED COMB.-AIR AND MAKE-UP AI DRYER ROOM. CLEARANCE ON DRYER VENT IS OK, 2" REQUIRED.
|
INSP - Final | 9/28/1995 | 9/29/1995 | 9/29/1995 | A | PART |
Alan Hauser
|
|
|
09/29/95 350 - SIGNED TEMPORARY OCCUPANCY BUT STILL NEED TO LOOK AT GAS INSTALLED.
|
INSP - Final | 9/28/1995 | 9/29/1995 | 9/29/1995 | A | PART |
Alan Hauser
|
|
|
09/29/95 350 - SIGNED TEMPORARY OCCUPANCY BUT STILL NEED TO LOOK AT GAS INSTALLED.
|
INSP - Framing/ Rough-in | 9/29/1995 | 9/29/1995 | 9/29/1995 | | PASS |
Alan Hauser
|
|
|
/ / 350 - FURNACE OK CRAWLSPACE NO PRESSURE TEST NEEDED.
|
INSP - Framing/ Rough-in | 9/29/1995 | 9/29/1995 | 9/29/1995 | | PASS |
Alan Hauser
|
|
|
/ / 350 - FURNACE OK CRAWLSPACE NO PRESSURE TEST NEEDED.
|
INSP - Gas pressure test | 9/15/1995 | 9/15/1995 | 9/15/1995 | P | PASS |
Alan Hauser
|
|
|
09/15/95 350 - SUTIE 103 GP -OK GAS PIPING #27617
|
INSP - Gas pressure test | 9/13/1995 | 9/14/1995 | 9/14/1995 | A | CANC |
|
|
|
09/14/95 326 - SUITE #103-$4,396.00 AS PER APPROVED PLANS AND SPECS
|