INSP - Final | 8/1/1996 | 8/1/1996 | 8/1/1996 | P | PASS |
|
|
|
08/01/96 326 - EINSPECTION Correction made. Final ok.
|
INSP - Final | 8/1/1996 | 8/1/1996 | 8/1/1996 | P | PASS |
|
|
|
08/01/96 326 - EINSPECTION Correction made. Final ok.
|
INSP - Final | 7/30/1996 | 7/30/1996 | 7/30/1996 | | NR |
|
|
|
/ / 326 - Not all corrections made - NO FINAL.
|
INSP - Final | 7/30/1996 | 7/30/1996 | 7/30/1996 | | NR |
|
|
|
/ / 326 - Not all corrections made - NO FINAL.
|
INSP - Final | 7/23/1996 | 7/23/1996 | 7/23/1996 | | FAIL |
Dave Lightfoot
|
|
|
/ / 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED SINGLE WALL VENT CLEARENCE B VENT CLEARENCE PIPE CONDENSATE
|
INSP - Final | 7/11/1996 | 7/11/1996 | 7/11/1996 | P | PASS |
|
|
|
07/11/96 326 - Final ok (No sign-off card).
|
INSP - Final | 7/11/1996 | 7/11/1996 | 7/11/1996 | P | PASS |
|
|
|
07/11/96 326 - Final ok (No sign-off card).
|
INSP - Framing/ Rough-in | 6/26/1996 | 6/26/1996 | 6/26/1996 | P | PASS |
|
|
|
06/26/96 326 - PARTIAL R/I TO COVER UP DUCT WORK R/I ok (2nd floor).
|
INSP - Framing/ Rough-in | 6/4/1996 | 6/4/1996 | 6/4/1996 | P | PASS |
|
|
|
06/04/96 326 - 1ST FLOOR R/I ok. (1st floor - underfloor duct)>
|
INSP - Framing/ Rough-in | 4/8/1996 | 4/8/1996 | 4/8/1996 | P | PART |
|
|
|
04/08/96 326 - NORTH ON HARTMAN OFF OF FRANKLIN-HVAC AS PER PLANS AND SP THE FORMAN ON THE JOB-###-####-PAGER * HOBSON JOB #2551-BLD95-1894-YOU M NOT GET HIM RIGHT AWAY JUST FOLLOW DIRECTIONS AND YOU SHOULD RUN RIGHT I THE JOB AS PER KA P
|