INSP - Final | 1/13/1997 | 1/13/1997 | 1/13/1997 | | PASS |
Dave Lightfoot
|
|
|
01/13/97 337 - FNL -OK FINAL
|
INSP - Final | 1/13/1997 | 1/13/1997 | 1/13/1997 | | PASS |
Dave Lightfoot
|
|
|
01/13/97 337 - FNL -OK FINAL
|
INSP - Final | 12/6/1996 | 12/9/1996 | 12/9/1996 | A | FAIL |
Dave Lightfoot
|
|
|
12/09/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Final | 12/6/1996 | 12/9/1996 | 12/9/1996 | A | FAIL |
Dave Lightfoot
|
|
|
12/09/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Final | 12/6/1996 | 12/6/1996 | 12/6/1996 | P | NR |
Dave Lightfoot
|
|
|
12/06/96 337 - not ready no access
|
INSP - Final | 12/6/1996 | 12/6/1996 | 12/6/1996 | P | NR |
Dave Lightfoot
|
|
|
12/06/96 337 - not ready no access
|
INSP - Rough-in & Gas Pressure | 9/19/1996 | 9/19/1996 | 9/19/1996 | P | CANC |
Dave Lightfoot
|
|
|
09/19/96 337 - REINSPECTION INSPECTION DONE 9/19/96 AM
|
INSP - Rough-in & Gas Pressure | 9/16/1996 | 9/17/1996 | 9/19/1996 | A | PASS |
Dave Lightfoot
|
|
|
09/18/96 337 - ANDIE WILL CALL YOU AND SEE IF YOU CAN DO IT 9-16 PM GP -OK GAS PIPING RGHN-OK ROUGH IN
|
INSP - Conference | 9/3/1996 | 9/3/1996 | 9/3/1996 | | PASS |
Dave Lightfoot
|
|
|
/ / 337 - CONFERENCE OK
|
INSP - Rough-in & Gas Pressure | 8/30/1996 | 8/30/1996 | 8/30/1996 | P | PASS |
Dave Lightfoot
|
|
|
08/30/96 337 - RGHN-OK ROUGH IN 1gas test fail
|
INSP - Framing/ Rough-in | 8/28/1996 | 8/28/1996 | 8/28/1996 | | FAIL |
Dave Lightfoot
|
|
|
/ / 337 - unit g 3 CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/ Rough-in | 8/28/1996 | 8/28/1996 | 8/28/1996 | | FAIL |
Dave Lightfoot
|
|
|
/ / 337 - unit g 1 CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|