INSP - Final | 10/30/1996 | 10/30/1996 | 10/30/1996 | P | PASS |
|
|
|
10/30/96 326 - SCHEDULED FOR YESTERDAY, YOU COULDN'T GET TO IT. THEY ARE FOR YOU, BUILDING WAITING FOR THEIR FINAL. Only a couple of items to be completed: install grilles, join ductwork, complete kitchen eqpt. installation.
|
INSP - Final | 10/30/1996 | 10/30/1996 | 10/30/1996 | P | PASS |
|
|
|
10/30/96 326 - SCHEDULED FOR YESTERDAY, YOU COULDN'T GET TO IT. THEY ARE FOR YOU, BUILDING WAITING FOR THEIR FINAL. Only a couple of items to be completed: install grilles, join ductwork, complete kitchen eqpt. installation.
|
INSP - Final | 10/29/1996 | 10/29/1996 | 10/29/1996 | P | NR |
|
|
|
10/29/96 326 - YMC TRAILER GO THERE Not done today - didn't get to it.
|
INSP - Final | 10/29/1996 | 10/29/1996 | 10/29/1996 | P | NR |
|
|
|
10/29/96 326 - YMC TRAILER GO THERE Not done today - didn't get to it.
|
INSP - Framing/ Rough-in | 9/30/1996 | 9/30/1996 | 9/30/1996 | P | PASS |
|
|
|
09/30/96 326 - R/I; 1st floor w/theater ok.
|
INSP - Framing/ Rough-in | 9/11/1996 | 9/11/1996 | 9/11/1996 | P | PASS |
|
|
|
09/11/96 326 - PARTIAL --CHECK IN AT YMC TRAILER All 2nd floor R/I ok. Signed Inspection report in trailer.
|
INSP - Framing/ Rough-in | 8/5/1996 | 8/5/1996 | 8/5/1996 | P | PART |
|
|
|
08/05/96 326 - Preliminary R/I survey of ductwork - all bldg. Correction hood exhaust ducts.
|
INSP - Framing/ Rough-in | 7/24/1996 | 7/24/1996 | 7/24/1996 | P | NR |
Alan Hauser
|
|
|
07/24/96 350 - NOT READY
|
INSP - Final | 7/23/1996 | 7/23/1996 | 7/23/1996 | P | NR |
Alan Hauser
|
|
|
07/23/96 350 - ONLY APLIED FOR PERMIT NOT READY FOR INSPECTIONS
|
INSP - Final | 7/23/1996 | 7/23/1996 | 7/23/1996 | P | NR |
Alan Hauser
|
|
|
07/23/96 350 - ONLY APLIED FOR PERMIT NOT READY FOR INSPECTIONS
|