INSP - Final | 2/7/1997 | 2/7/1997 | 2/20/1997 | P | PASS |
Dave Lightfoot
|
|
|
|
INSP - Final | 2/7/1997 | 2/7/1997 | 2/20/1997 | P | PASS |
Dave Lightfoot
|
|
|
|
INSP - Final | 2/7/1997 | 2/7/1997 | 2/7/1997 | | PASS |
Dave Lightfoot
|
|
|
02/07/97 337 - FNL -OK FINAL sign perm occ card
|
INSP - Final | 2/7/1997 | 2/7/1997 | 2/7/1997 | | PASS |
Dave Lightfoot
|
|
|
02/07/97 337 - FNL -OK FINAL sign perm occ card
|
INSP - Final | 2/5/1997 | 2/5/1997 | 2/5/1997 | | FAIL |
Dave Lightfoot
|
|
|
/ / 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Partial final | 2/4/1997 | 2/4/1997 | 2/4/1997 | P | CANC |
Dave Lightfoot
|
|
|
02/04/97 337 - 1ST AND 2ND FLOOR..SOUTH WING they called and canceled untill 2/5/97
|
INSP - Partial final | 1/14/1997 | 1/14/1997 | 1/14/1997 | P | PART |
Dave Lightfoot
|
|
|
01/14/97 337 - NORTH AND EAST WING..1ST AND 2ND FLOORS sign temp occ card
|
INSP - Gas pressure test | 1/8/1997 | 1/8/1997 | 1/8/1997 | P | PASS |
Dave Lightfoot
|
|
|
01/08/97 337 - PARTIAL GAS TEST KITCHEN ONLY GP -OK GAS PIPING
|
INSP - Framing/ Rough-in | 12/12/1996 | 12/13/1996 | 12/13/1996 | P | PASS |
Dave Lightfoot
|
|
|
12/13/96 337 - 1ST FLOOR SOUTH WING RGHN-OK ROUGH IN
|
INSP - Rough-in & Gas Pressure | 12/3/1996 | 12/3/1996 | 12/3/1996 | P | PASS |
Dave Lightfoot
|
|
|
12/03/96 337 - REIN ON GAS TEST 1ST FLOOR EAST WING. GP -OK GAS PIPING 1st floor east wing r/i ok
|
INSP - Framing/ Rough-in | 11/25/1996 | 11/25/1996 | 11/25/1996 | P | PASS |
Dave Lightfoot
|
|
|
11/25/96 337 - rooms only on south wing of 2nd floor RGHN-OK ROUGH IN rooms only
|
INSP - Framing/ Rough-in | 11/25/1996 | 11/25/1996 | 11/25/1996 | P | PASS |
Dave Lightfoot
|
|
|
11/25/96 337 - 2 corridor east wing RGHN-OK ROUGH IN 2nd floor corridor
|
INSP - Framing/ Rough-in | 11/22/1996 | 11/25/1996 | 11/25/1996 | P | PASS |
Dave Lightfoot
|
|
|
11/25/96 337 - SECOND FLOOR CORR. EAST WING RGHN-OK ROUGH IN 2nd floor east wing
|
INSP - Framing/ Rough-in | 11/13/1996 | 11/13/1996 | 11/13/1996 | P | PASS |
Dave Lightfoot
|
|
|
11/13/96 337 - ROOMS ONLY ON UPSTAIRS EAST WING partial 2nd floor r/i for rooms only ok
|
INSP - Gas pressure test | 11/13/1996 | 11/13/1996 | 11/13/1996 | P | NR |
Dave Lightfoot
|
|
|
11/13/96 337 - PARTIAL GAS TEST/NORTH AND EAST WINGS gas test not ready
|
INSP - Framing/ Rough-in | 11/8/1996 | 11/12/1996 | 11/12/1996 | A | PASS |
Dave Lightfoot
|
|
|
11/12/96 337 - reinspection/ 1st floor north wing north wing 1st and 2nd floor r/i ok
|
INSP - Framing/ Rough-in | 11/8/1996 | 11/8/1996 | 11/8/1996 | | PART |
Dave Lightfoot
|
|
|
11/08/96 337 - ok for 2nd floor coridor rock r/i not complete
|
INSP - Framing/ Rough-in | 11/4/1996 | 11/4/1996 | 11/4/1996 | | PASS |
Dave Lightfoot
|
|
|
/ / 337 - partial 2nd fioor north end only r/i ok
|
INSP - Framing/ Rough-in | 10/31/1996 | 10/31/1996 | 10/31/1996 | P | NR |
Dave Lightfoot
|
|
|
10/31/96 337 - N END OF BUILDING ONLY not ready need to see story on this
|