INSP - Final | 1/12/1998 | 1/13/1998 | 1/13/1998 | A | PASS |
Alan Hauser
|
|
|
01/13/98 350 - final, signed final occ. card
|
INSP - Final | 1/12/1998 | 1/13/1998 | 1/13/1998 | A | PASS |
Alan Hauser
|
|
|
01/13/98 350 - final, signed final occ. card
|
INSP - Final | 12/18/1997 | 12/18/1997 | 12/18/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - drains still not seperated
|
INSP - Final | 12/18/1997 | 12/18/1997 | 12/18/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - drains still not seperated
|
INSP - Final | 12/10/1997 | 12/10/1997 | 12/10/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - drains not fixed as always, left notice last inspection with fees assessed
|
INSP - Final | 12/10/1997 | 12/10/1997 | 12/10/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - drains not fixed as always, left notice last inspection with fees assessed
|
INSP - Final | 12/10/1997 | 12/10/1997 | 12/10/1997 | P | FAIL |
Alan Hauser
|
|
|
12/10/97 350 - CHURCH not ready for inspection
|
INSP - Final | 12/10/1997 | 12/10/1997 | 12/10/1997 | P | FAIL |
Alan Hauser
|
|
|
12/10/97 350 - CHURCH not ready for inspection
|
INSP - Final | 12/1/1997 | 12/1/1997 | 12/1/1997 | | PART |
Alan Hauser
|
|
|
/ / 350 - corrections fixed, except still need condensate drains chang
|
INSP - Final | 12/1/1997 | 12/1/1997 | 12/1/1997 | | PART |
Alan Hauser
|
|
|
/ / 350 - corrections fixed, except still need condensate drains chang
|
INSP - Final | 11/25/1997 | 11/25/1997 | 11/26/1997 | P | CANC |
Dave Lightfoot
|
|
|
11/26/97 337 - will be done by alan
|
INSP - Final | 11/25/1997 | 11/25/1997 | 11/26/1997 | P | CANC |
Dave Lightfoot
|
|
|
11/26/97 337 - will be done by alan
|
INSP - Final | 11/25/1997 | 11/25/1997 | 11/25/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - no final, still corrections posted
|
INSP - Final | 11/25/1997 | 11/25/1997 | 11/25/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - no final, still corrections posted
|
INSP - Final | 11/10/1997 | 11/10/1997 | 11/10/1997 | | PART |
Alan Hauser
|
|
|
/ / 350 - signed temp. final card only
|
INSP - Final | 11/10/1997 | 11/10/1997 | 11/10/1997 | | PART |
Alan Hauser
|
|
|
/ / 350 - signed temp. final card only
|
INSP - Final | 11/7/1997 | 11/7/1997 | 11/7/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - couldn't signe temp. final, corrections on flue connectors i side, unvented w/h in basement hooked up to gasline
|
INSP - Final | 11/7/1997 | 11/7/1997 | 11/7/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - couldn't signe temp. final, corrections on flue connectors i side, unvented w/h in basement hooked up to gasline
|
INSP - Framing/ Rough-in | 11/3/1997 | 11/3/1997 | 11/3/1997 | | PART |
Alan Hauser
|
|
|
/ / 350 - meet with hvac contractor and mech. engineer to go over corr
|
INSP - Framing/ Rough-in | 10/28/1997 | 10/28/1997 | 10/28/1997 | P | FAIL |
Alan Hauser
|
|
|
10/28/97 350 - PARTIAL TOP FLOOR no r/i, many corrections posted with job supt.
|
INSP - Framing/ Rough-in | 7/10/1997 | 7/11/1997 | 7/11/1997 | A | PART |
Alan Hauser
|
|
|
07/11/97 350 - WOULD LIKE 8:30 9 O'CLOCK IF AT ALL POSSIBLE. r/i ok for areas with hard ceilings, will need inspection on accessible areas later and basement
|