INSP - Final | 3/10/1997 | 3/11/1997 | 3/11/1997 | A | PASS |
Alan Hauser
|
|
|
03/11/97 350 - final
|
INSP - Final | 3/10/1997 | 3/11/1997 | 3/11/1997 | A | PASS |
Alan Hauser
|
|
|
03/11/97 350 - final
|
INSP - Gas pressure test | 2/26/1997 | 2/27/1997 | 2/27/1997 | A | PART |
Alan Hauser
|
|
|
02/27/97 350 - pt ok, signed temp. occ. card
|
INSP - Conference | 2/26/1997 | 2/26/1997 | 2/26/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - talked to contractor (robin) about gas piping and temp. fina
|
INSP - Partial final | 2/25/1997 | 2/25/1997 | 2/25/1997 | P | FAIL |
Alan Hauser
|
|
|
02/25/97 350 - partial final/north bld/ re-inspection on gas test no final, ductwork ok, but gas pipe to two new units on roof is undersiz
|
INSP - Gas pressure test | 2/18/1997 | 2/19/1997 | 2/19/1997 | A | FAIL |
Alan Hauser
|
|
|
02/19/97 350 - BEHIND MICHAELS FURNITURE pressure test failed on 11#
|