INSP - Final | 6/15/1998 | 6/15/1998 | 6/15/1998 | P | PASS |
Dave Lightfoot
|
|
|
06/15/98 337 - ###-####----FINAL SHELL & CORE FNL -OK FINAL no occ card on site
|
INSP - Final | 6/15/1998 | 6/15/1998 | 6/15/1998 | P | PASS |
Dave Lightfoot
|
|
|
06/15/98 337 - ###-####----FINAL SHELL & CORE FNL -OK FINAL no occ card on site
|
INSP - Final | 10/22/1997 | 10/22/1997 | 10/22/1997 | | NR |
Dave Lightfoot
|
|
|
/ / 337 - need hood wash down
|
INSP - Hoods | 10/20/1997 | 10/20/1997 | 10/20/1997 | | NR |
Dave Lightfoot
|
|
|
/ / 337 - make up air unit not ready also need to interlock with hood
|
INSP - Framing/ Rough-in | 10/17/1997 | 10/17/1997 | 10/17/1997 | | PASS |
Dave Lightfoot
|
|
|
/ / 337 - part rough in event kit hood ok
|
INSP - Final | 9/10/1997 | 9/10/1997 | 9/10/1997 | | PASS |
Dave Lightfoot
|
|
|
/ / 337 - temp occ for event area
|
INSP - Conference | 8/20/1997 | 8/20/1997 | 8/20/1997 | | PASS |
Dave Lightfoot
|
|
|
/ / 337 - 1 hr walk through
|
INSP - Framing/ Rough-in | 8/7/1997 | 8/7/1997 | 8/7/1997 | | PASS |
Dave Lightfoot
|
|
|
/ / 337 - partial r/i event floor 1st 2nd and 3rd floors ok
|
INSP - Framing/ Rough-in | 8/5/1997 | 8/6/1997 | 8/6/1997 | A | CANC |
Alan Hauser
|
|
|
08/06/97 350 - ###-#### Brad White call before you go out or on site tha to be done by #337
|
INSP - Framing/ Rough-in | 8/6/1997 | 8/6/1997 | 8/6/1997 | | CANC |
Dave Lightfoot
|
|
|
/ / 337 - this will be done 8/07/97 am
|
INSP - Conference | 4/3/1997 | 4/3/1997 | 4/3/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - talked with contractor about different parts of job
|
INSP - Conference | 4/2/1997 | 4/2/1997 | 4/2/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - talked with brad, will meet 9 a.m. thur.
|
INSP - Conference | 4/2/1997 | 4/2/1997 | 4/2/1997 | P | PASS |
Alan Hauser
|
|
|
04/02/97 350 - CALL BRAD WHITE ###-#### CEL PHONE SO HE CAN MEET WITH YO will meet in morning
|