INSP - Final | 12/16/1997 | 12/16/1997 | 12/16/1997 | | PART |
Alan Hauser
|
|
|
/ / 350 - signed temp. occ.
|
INSP - Final | 12/16/1997 | 12/16/1997 | 12/16/1997 | | PART |
Alan Hauser
|
|
|
/ / 350 - signed temp. occ.
|
INSP - Final | 12/10/1997 | 12/10/1997 | 12/10/1997 | P | PART |
Alan Hauser
|
|
|
12/10/97 350 - please before 3:30 walked through, still not completly finished
|
INSP - Final | 12/10/1997 | 12/10/1997 | 12/10/1997 | P | PART |
Alan Hauser
|
|
|
12/10/97 350 - please before 3:30 walked through, still not completly finished
|
INSP - Conference | 12/1/1997 | 12/3/1997 | 12/3/1997 | P | PASS |
Alan Hauser
|
|
|
12/03/97 350 - Conference w/Doug McAlvain, etc. on duct work at 2:00 tod went over what had been finished, all above ceiling ok
|
INSP - Framing/ Rough-in | 12/2/1997 | 12/3/1997 | 12/3/1997 | A | PASS |
Alan Hauser
|
|
|
12/03/97 350 - fire damper all smoke/fire dampers looked at and operating, all above ceiling areas at
|
INSP - Framing/ Rough-in | 12/1/1997 | 12/1/1997 | 12/1/1997 | P | PART |
Alan Hauser
|
|
|
12/01/97 350 - looked at all smoke/fire dampers upper levels
|
INSP - Framing/ Rough-in | 11/25/1997 | 11/25/1997 | 11/25/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - went over smoke fire damper operation, need access panels at inspection
|
INSP - Framing/ Rough-in | 11/24/1997 | 11/24/1997 | 11/24/1997 | P | PASS |
Alan Hauser
|
|
|
11/24/97 350 - looked at all fire dampers in theater ceilings
|
INSP - Framing/ Rough-in | 10/31/1997 | 10/31/1997 | 10/31/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - looked at part. r/i for lobby area
|
INSP - Framing/ Rough-in | 10/30/1997 | 10/30/1997 | 10/30/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - went by looked at area upstairs to be cover, ok to cover
|
INSP - Framing/ Rough-in | 10/30/1997 | 10/30/1997 | 10/30/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - part. r/i for theater areas, ok for ceiling tile
|