INSP - Final | 1/5/1998 | 1/5/1998 | 1/5/1998 | P | PASS |
Alan Hauser
|
|
|
01/05/98 350 - final,signed final occ. card
|
INSP - Final | 1/5/1998 | 1/5/1998 | 1/5/1998 | P | PASS |
Alan Hauser
|
|
|
01/05/98 350 - final,signed final occ. card
|
INSP - Gas pressure test | 10/24/1997 | 10/27/1997 | 10/27/1997 | A | PASS |
Alan Hauser
|
|
|
10/27/97 350 - Scheduled by Hello! on 10/24/97 at 14:14:59. pt ok for whole building
|
INSP - Gas pressure test | 10/23/1997 | 10/23/1997 | 10/23/1997 | P | FAIL |
Alan Hauser
|
|
|
10/23/97 350 - Scheduled by Hello! on 10/23/97 at 06:03:55. pt failed, pressure down
|
INSP - Gas pressure test | 10/20/1997 | 10/20/1997 | 10/20/1997 | P | PASS |
Alan Hauser
|
|
|
10/20/97 350 - Scheduled by Hello! on 10/20/97 at 11:15:59. pt ok for new gas piping
|
INSP - Conference | 10/16/1997 | 10/16/1997 | 10/16/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - went over duct work in basement with contractor
|
INSP - Framing/ Rough-in | 10/16/1997 | 10/16/1997 | 10/16/1997 | P | PASS |
Alan Hauser
|
|
|
10/16/97 350 - Scheduled by Hello! on 10/16/97 at 06:43:59. r/i ok finally
|
INSP - Framing/ Rough-in | 10/15/1997 | 10/15/1997 | 10/15/1997 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - no r/i, corrections from 10/7 not fixed, $42 reinspection fe
|
INSP - Framing/ Rough-in | 10/14/1997 | 10/14/1997 | 10/14/1997 | P | CANC |
Jim Sly
|
|
|
10/14/97 316 - rein Gave to Alan H.
|
INSP - Rough-in & Gas Pressure | 10/6/1997 | 10/7/1997 | 10/7/1997 | A | PART |
Alan Hauser
|
|
|
10/07/97 350 - DENTAL OFFICE no r/i corrections left with building supt., pt ok ì
|