INSP - Final | 6/17/1998 | 6/17/1998 | 6/17/1998 | | PASS |
Alan Hauser
|
|
|
/ / 350 - signed final on shell, which all work was under
|
INSP - Final | 6/17/1998 | 6/17/1998 | 6/17/1998 | | PASS |
Alan Hauser
|
|
|
/ / 350 - signed final on shell, which all work was under
|
INSP - Final | 6/11/1998 | 6/11/1998 | 6/11/1998 | | PART |
Alan Hauser
|
|
|
/ / 350 - went over hvac system with contractor, they are done and rea occ. card on site yet
|
INSP - Final | 6/11/1998 | 6/11/1998 | 6/11/1998 | | PART |
Alan Hauser
|
|
|
/ / 350 - went over hvac system with contractor, they are done and rea occ. card on site yet
|
INSP - Framing/ Rough-in | 3/11/1998 | 3/11/1998 | 3/11/1998 | | PASS |
Alan Hauser
|
|
|
/ / 350 - 2nd and 3rd flr. ceilings ok for cover
|
INSP - Framing/ Rough-in | 3/3/1998 | 3/3/1998 | 3/3/1998 | | PASS |
Alan Hauser
|
|
|
/ / 350 - r/i on 1st flr. duct in shafts, ok to cover
|
INSP - Framing/ Rough-in | 2/5/1998 | 2/6/1998 | 2/6/1998 | A | PASS |
Alan Hauser
|
|
|
02/06/98 350 - floyd farley cell ###-#### HVAC looked at all duct above ceiling and all roof top units. next inspectio diffusers in ceiling, before tile
|