Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberMEC98-01900
StatusFinaled
Name PARAGON PLUMBING INC
Site Address 456 N KIMBALL PL
Project NameAMERICAN DIRECT II
Customer Number 
ePlanReview 
Description
4/29/98-AMERICAN DIRECT CREDIT CORPORATE OFFICE (PHASE II) * ENTIRE ROOF-RUN APPROX. 575 FT GAS PIPING TO ELEVEN LOCATIONS FOR FUTURE ROOF TOP UNITS. FINAL CERTIFICATE OF VALUE
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final6/23/19986/24/19986/24/1998APASS
DetailsAlan Hauser
06/24/98 350 - gas piping finished as per plan
INSP - Final6/23/19986/24/19986/24/1998APASS
DetailsAlan Hauser
06/24/98 350 - gas piping finished as per plan
INSP - Framing/ Rough-in6/23/19986/24/19986/24/1998APASS
DetailsAlan Hauser
06/24/98 350 - as per plan
INSP - Framing/ Rough-in6/16/19986/17/19986/17/1998AFAIL
DetailsAlan Hauser
06/17/98 350 - PRESSURE TEST. WAS SENT IN 6/16/ BUT NOT ENTERED ###-#### went by on 16th, had wrong gage on and gage was pegged out, no inspectio
INSP - Gas pressure test6/16/19986/16/19986/16/1998 FAIL
DetailsAlan Hauser
/ / 350 - test failed, gage is pegged out, also used wrong gage, 60# g