Permit Information
Permit NumberMEC98-03284
StatusExpired
Name EMPIRE HEATING
Site Address 9543 W EMERALD ST
Project NameSAILFISH PLACE
Customer Number 
ePlanReview 
Description
10-06-98 NEW CONSTRUCTION 4 GAS PAK ROOF TOP UNITS 2 UNIT HEATERS IN BAY AREA VENTING BATHROOM FANS $10000.00 INITIAL CERTIFICATE OF VALUE AL
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Framing/ Rough-in12/11/199812/14/199812/11/1998APART
DetailsAlan Hauser
12/11/98 350 - pt ok, corrections on regulators
INSP - Final12/10/199812/11/199812/11/1998APART
DetailsAlan Hauser
12/11/98 350 - pt ok, still corrections on regulator
INSP - Final12/10/199812/11/199812/11/1998APART
DetailsAlan Hauser
12/11/98 350 - pt ok, still corrections on regulator
INSP - Final11/10/199811/12/199811/12/1998APASS
DetailsAlan Hauser
11/12/98 350 - signed final occ
INSP - Final11/10/199811/12/199811/12/1998APASS
DetailsAlan Hauser
11/12/98 350 - signed final occ
INSP - Framing/ Rough-in11/4/199811/6/199811/6/1998APART
DetailsAlan Hauser
11/06/98 350 - WALK THROUGH INSPECTION ONLY, meet with contractor about
INSP - Conference10/23/199810/23/199810/23/1998 PASS
DetailsAlan Hauser
/ / 350 - meet with gas co., about gas piping test.
INSP - Framing/ Rough-in10/21/199810/22/199810/22/1998APART
DetailsAlan Hauser
10/21/98 350 - pt only, piping not approved until drawings received
INSP - Framing/ Rough-in10/12/199810/13/199810/13/1998AFAIL
DetailsAlan Hauser
10/13/98 350 - no approved mech. plans with approved set, left notice
INSP - Framing/ Rough-in10/6/199810/7/199810/7/1998ACANC
DetailsTom Arcoraci
10/07/98 408 - SHAWNA ###-#### R/I ONLY ON THE LOWER LEVEL done by 350
INSP - Rough-in & Gas Pressure10/7/199810/7/199810/7/1998 FAIL
DetailsAlan Hauser
/ / 350 - no one on site, left notice to meet me on site