INSP - Final | 2/10/1999 | 2/11/1999 | 2/11/1999 | A | PASS |
Alan Hauser
|
|
|
02/11/99 350 - gas range didn't meet manufactures clearances, so was rem
|
INSP - Final | 2/10/1999 | 2/11/1999 | 2/11/1999 | A | PASS |
Alan Hauser
|
|
|
02/11/99 350 - gas range didn't meet manufactures clearances, so was rem
|
INSP - Final | 2/10/1999 | 2/10/1999 | 2/10/1999 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - DON'T HAVE REQUIRED CLEARANCES AT GAS RANGE, AS PER MANUFACT
|
INSP - Final | 2/9/1999 | 2/10/1999 | 2/10/1999 | A | FAIL |
Jim Sly
|
|
|
02/10/99 316 - Done by Alan H.
|
INSP - Final | 2/10/1999 | 2/10/1999 | 2/10/1999 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - DON'T HAVE REQUIRED CLEARANCES AT GAS RANGE, AS PER MANUFACT
|
INSP - Final | 2/9/1999 | 2/10/1999 | 2/10/1999 | A | FAIL |
Jim Sly
|
|
|
02/10/99 316 - Done by Alan H.
|
INSP - Final | 2/5/1999 | 2/5/1999 | 2/5/1999 | | FAIL |
Russ Owen
|
|
|
/ / 407 - LEFT CORRECTION ON UNIT.
|
INSP - Final | 2/5/1999 | 2/5/1999 | 2/5/1999 | | FAIL |
Russ Owen
|
|
|
/ / 407 - LEFT CORRECTION ON UNIT.
|
INSP - Final | 2/5/1999 | 2/5/1999 | 2/5/1999 | P | FAIL |
Carl Dependahl
|
|
|
02/05/99 340 - per 325###-####
|
INSP - Final | 2/5/1999 | 2/5/1999 | 2/5/1999 | P | FAIL |
Carl Dependahl
|
|
|
02/05/99 340 - per 325###-####
|
INSP - Framing/ Rough-in | 12/15/1998 | 12/16/1998 | 12/16/1998 | A | PASS |
Tom Arcoraci
|
|
|
12/16/98 408 - ###-#### REINSPECTION
|
INSP - Framing/ Rough-in | 12/14/1998 | 12/15/1998 | 12/15/1998 | A | PART |
Jim Sly
|
|
|
12/15/98 316 - Rough in OK but test guage for gas line not trustworthy..
|