Final | 4/27/2000 | 4/28/2000 | 4/28/2000 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 04/27/2000 at 15:14:34. Contact: ###-####.
|
Final | 4/21/2000 | 4/21/2000 | 4/21/2000 | P | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 04/21/2000 at 08:13:05. Contact: ###-####.
|
Pressure Test | 2/7/2000 | 2/7/2000 | 2/7/2000 | P | PART |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 02/07/2000 at 11:17:12. Contact: ###-####. North roof area
|
Pressure Test | 1/28/2000 | 1/28/2000 | 1/28/2000 | P | PART |
Dave Lightfoot
|
|
|
###-#### gas piping on south end of bldg ok 1/31/00 8:29:40 AM
|
INSP - Framing/ Rough-in | 8/23/1999 | 8/23/1999 | 8/23/1999 | P | PASS |
Alan Hauser
|
|
|
08/23/99 350 - DAVE ###-####. GAS
|
INSP - Framing/ Rough-in | 7/6/1999 | 7/7/1999 | 7/7/1999 | A | PART |
Alan Hauser
|
|
|
07/07/99 350 - underground piping ok to new gym
|