Final | 1/10/2000 | 1/11/2000 | 1/11/2000 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 01/10/2000 at 09:21:16. Contact: ###-####. Final ok.
|
Final | 12/14/1999 | 12/15/1999 | 12/15/1999 | A | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 13:53:16. Contact: ###-####. Need electrical.
|
Final | 12/10/1999 | 12/10/1999 | 12/10/1999 | P | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 12/10/1999 at 08:11:02. Contact: ###-####. Not ready.
|
Rough-in | 9/22/1999 | 9/22/1999 | 9/22/1999 | P | PASS |
Jim Sly
|
|
|
sabrina ###-#### r/I Gas tag #033165
|
Pressure Test | 9/10/1999 | 9/10/1999 | 9/10/1999 | P | FAIL |
Dixie Fellows
|
|
|
NOT READY
|