Final | 12/31/1999 | 1/3/2000 | 1/3/2000 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/31/1999 at 08:40:47. Contact: ###-####.
|
Final | 1/3/2000 | 1/3/2000 | 1/3/2000 | P | PASS |
Russ Owen
|
|
|
|
Final | 12/30/1999 | 1/3/2000 | 12/31/1999 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/30/1999 at 16:34:13. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 12/31/1999 at 08:39:51.
|
Final | 12/27/1999 | 12/28/1999 | 12/27/1999 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/27/1999 at 15:11:56. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 12/27/1999 at 16:12:33.
|
Final | 11/12/1999 | 11/15/1999 | 11/15/1999 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/12/1999 at 16:26:16. Contact: ###-####. Not ready, per Job Supper. Just started sheetrocking.
|
Final | 11/12/1999 | 11/12/1999 | 11/12/1999 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/12/1999 at 11:18:39. Contact: ###-####.
|
Rough-in | 10/22/1999 | 10/22/1999 | 10/22/1999 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/22/1999 at 09:22:13. Contact: ###-####. R/I gas ok
|
Rough-in | 10/21/1999 | 10/21/1999 | 10/21/1999 | P | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 10/21/1999 at 08:47:09. Contact: ###-####. Corrections
|