Final | 1/12/2000 | 1/13/2000 | 1/13/2000 | A | PASS |
Alan Hauser
|
|
|
|
Final | 1/11/2000 | 1/12/2000 | 1/11/2000 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 01/11/2000 at 15:40:16. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 01/11/2000 at 17:19:11.
|
Final | 1/11/2000 | 1/11/2000 | 1/11/2000 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 01/11/2000 at 08:03:23. Contact: ###-####. Talked to Ray B. about corrections.
|
Rough-in | 10/18/1999 | 10/18/1999 | 10/18/1999 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/18/1999 at 10:34:06. Contact: ###-####. R/I & gas ok
|
Rough-in | 10/14/1999 | 10/15/1999 | 10/15/1999 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/14/1999 at 13:02:18. Contact: ###-####. C/N.. Pressure test fail & misc. corr.
|