Final | 11/4/1999 | 11/5/1999 | 11/5/1999 | A | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 11/04/1999 at 15:42:06. Contact: ###-####. Provide upper combustion air.
|
Final | 10/28/1999 | 10/28/1999 | 10/29/1999 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 10/28/1999 at 08:12:58. Contact: ###-####. No answer @ door 2 rings.
|
Final | 10/26/1999 | 10/27/1999 | 10/27/1999 | A | FAIL |
Dave Lightfoot
|
|
|
Mike ###-#### Need combustion air.
|
Final | 10/25/1999 | 10/25/1999 | 10/25/1999 | P | FAIL |
Dave Lightfoot
|
|
|
late as possible mike ###-#### gas test w/h and furnace Not ready
|