FIR-Conference | 1/14/2005 | 2/3/2005 | 2/3/2005 | A | PASS |
Rick Jackson
|
|
|
Follow up to check FD access///// The pad is complete and placement is within the 150 ft criteria 2/3/2005 11:41:30 AM
|
FIR-Final | 12/15/2004 | 1/14/2005 | 1/14/2005 | A | NR |
Rick Jackson
|
|
|
Follow up for FD access This was scheduled by inspector - no work accomplished; rescheduled for 2/3/05 1/14/2005 10:21:42 AM
|
FIR-Conference | 11/30/2004 | 12/15/2004 | 12/15/2004 | A | NR |
Rick Jackson
|
|
|
Follow up to see if any site work has started No work has started for the new pad - rescheduled another site visit for 01/14/05 12/15/2004 10:57:13 AM
|
FIR-Final | 10/29/2004 | 11/30/2004 | 11/30/2004 | A | NR |
Rick Jackson
|
|
|
Follow up for location of pad - Matt ###-#### No site work has begun - scheduled another site visit for 12/15/04 11/30/2004 11:30:29 AM
|
FIR-Final | 9/29/2004 | 10/29/2004 | 10/29/2004 | A | NR |
Rick Jackson
|
|
|
verify FD access roads, hydrants, and location of foundation as shown on plans for FD accessibility. Structures are to be temporary only. Talked to Matt (###-####) and they plan to start this project at the end of Nov or early Dec; rescheduled for 11/30 10/29/2004 11:58:23 AM
|