MIS-Aging Inspection | 7/2/2020 | 7/2/2020 | 7/8/2020 | | DONE |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | PASS |
Jim Storey
|
|
|
|
PLM-Final | 3/12/2020 | 3/12/2020 | 3/13/2020 | P | PASS |
Eric Strole
|
|
|
Marcus Phone #: ###-####
|
MEC-Final | 3/12/2020 | 3/12/2020 | 3/12/2020 | P | PASS |
Jack Reynolds
|
|
|
Marcus Phone #: ###-#### - mechanical final ok and per City approved plans
|
MEC-Conference | 8/5/2019 | 8/5/2019 | 8/5/2019 | P | DONE |
Jack Reynolds
|
|
|
Follow up inspection on mechanical ventilation - Talked with Facilities Manager Jerad about where they are in getting the mechanical ventilation engineered for their operations. He stated the owner is working on this with an engineer currently.
|
MEC-Final | 7/1/2019 | 7/1/2019 | 7/2/2019 | P | FAIL |
Jack Reynolds
|
|
|
Jerad Phone #: ###-#### -Need to have engineered drawings from an Idaho licensed engineer for mechanical ventilation of site operations which include painting, welding, and cutting shipping containers. Drawings will then need to be submitted to the City of Boise for approval
|
ELE-Final | 7/1/2019 | 7/1/2019 | 7/1/2019 | P | DONE |
James Ady
|
|
|
Jerad Phone #: ###-#### No answer could not see any electrical being done
|
PLM-Final | 7/1/2019 | 7/1/2019 | 7/1/2019 | P | PART |
Eric Strole
|
|
|
Jerad Phone #: ###-####-Need to install a DBCA for premis protection with a thermal expantion tank.
|