BLD-Conference | 12/10/2019 | 1/6/2020 | 1/6/2020 | A | DONE |
Dave Hannah
|
|
|
Check to see if any work has taken place. no sign of any work beening done
|
BLD-Conference | 11/26/2019 | 12/10/2019 | 12/10/2019 | A | DONE |
Mike Jordan
|
|
|
Check to see if any work is taken place. No evidence of any further work taken place.
|
Set Bond Amount | 10/22/2019 | 11/26/2019 | 11/26/2019 | A | FAIL |
Mike Jordan
|
|
|
End of 25 day notice. Another stop work was posted. Appears that not work other than demo is completed. Also no permits have been issued as of today.
|
BLD-Conference | 10/24/2019 | 10/31/2019 | 10/31/2019 | A | DONE |
Mike Jordan
|
|
|
Checked jobsite. Appears no work has taken place. Both 5 day and 25 day notices still posted.
|
BLD-Conference | 10/22/2019 | 10/24/2019 | 10/24/2019 | A | DONE |
Mike Jordan
|
|
|
Check to see if any work is going on.... No work.
|
BLD-Conference | 10/15/2019 | 10/22/2019 | 10/22/2019 | A | DONE |
Mike Jordan
|
|
|
Check on status, issue 25 day notice.... 25 day notice issued. No one on site, no new work.
|
BLD-Conference | 10/1/2019 | 10/15/2019 | 10/15/2019 | A | FAIL |
Mike Jordan
|
|
|
Check on status... No progress has been made on obtaining a building permit. Appears no work has taken place except for demo work. Contractor not on site. A 5 day notice has been issued.
|
BLD-Conference | 9/17/2019 | 10/1/2019 | 10/1/2019 | A | FAIL |
Mike Jordan
|
|
|
Check on status.... Contractor has not submitted plans, demo is completed. Noted contractor not on site. A correction notice was issued to submit plans to obtain a building permit and obtain any other required MEP premits.
|
BLD-Conference | 9/17/2019 | 9/17/2019 | 9/17/2019 | A | DONE |
Mike Jordan
|
|
|
Noted demo work going inside of home. Removing sheet rock and repairing water damage. Will also remove plumbing fixtures. Noted to contractor (Conrad) to submit plans and obtain a building permit. Reroof and siding as well.
|