BLD-Conference | 8/4/2020 | 8/4/2020 | 8/4/2020 | P | CANC |
Brandon Shaw
|
|
|
|
BLD-Conference | 11/14/2019 | 11/18/2019 | 11/18/2019 | A | DEFR |
Brandon Shaw
|
|
|
Per phone conversation with Craig, plans should be ready for submittal within the next two weeks...
|
BLD-Conference | 10/3/2019 | 10/3/2019 | 10/4/2019 | P | DEFR |
Brandon Shaw
|
|
|
Craig Brascher, PE, SE, with Ally Structural Consulting called and let me know he has been on site and has requested that the drywall around the two beams and colunms be removed, for futher inspection. I advised Craig, Bob and I had concern in at least two to three other areas that need futher review as well...
|
BLD-Conference | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Conference | 9/27/2019 | 9/27/2019 | 9/27/2019 | A | CANC |
Brandon Shaw
|
|
|
|
Set Bond Amount | 9/24/2019 | 9/27/2019 | 9/27/2019 | A | CANC |
Brandon Shaw
|
|
|
|
BLD-Conference | 9/23/2019 | 9/24/2019 | 9/24/2019 | A | DEFR |
Brandon Shaw
|
|
|
Immediate action required... C.N. left with maintenance superviser... Follow up in three days...
|
BLD-Conference | 9/24/2019 | 9/24/2019 | 9/24/2019 | A | DONE |
Bob Archibald
|
|
|
CN issued requiring engineering analysis and building permit to repair water damaged beams/columns and ceiling in parking garage.
|