INSP-Final | 3/4/2015 | 3/5/2015 | 3/5/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The surface mounted lights in the garage have been rotated out of the way.
|
INSP-Final | 3/3/2015 | 3/4/2015 | 3/4/2015 | P | FAIL |
Troy Cobbley
|
|
|
All items appear ok except the four pendant heads in the garage are blocked by surface mounted lights.
|
INSP-Final | 1/16/2015 | 1/20/2015 | 1/20/2015 | A | PART |
Troy Cobbley
|
|
|
Only Lot 10 (3606) is passed. Lot 9 is not complete.
|
INSP-Final | 1/11/2015 | 1/12/2015 | 1/12/2015 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Anthony due to notification issues.
|
INSP-Sprinkler Rough-in | 11/17/2014 | 11/17/2014 | 11/17/2014 | P | PASS |
Troy Cobbley
|
|
|
As-built/revised installation verified. Tenting verified. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2014 | 11/4/2014 | 11/4/2014 | P | PART |
Troy Cobbley
|
|
|
The hydro test passed for both overhead systems. Heads have been added in the fire places and the missing head provided in the lower level south room. As per previous correction comment as-builts need to be provided. Piping can not be covered until the as-builts are addressed and tenting inspection has been performed.
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2014 | 10/31/2014 | 10/31/2014 | P | FAIL |
Craig D. Hanson
|
|
|
heads need to installed in fireplace chase's. head needs installed in new room 1st floor S unit. As builts need to be submitted. Re-hydro after instilation of heads.
|