INSP-Final | 7/13/2016 | 7/15/2016 | 7/15/2016 | A | PASS |
Katie Marron
|
|
|
Unit 3594 final test completed satisfactory. Scope of work complete. Permit Finaled.
|
INSP-Final | 6/23/2016 | 6/28/2016 | 6/28/2016 | A | PART |
Katie Marron
|
|
|
Walk through completed. Flow switch was not wired so acceptance test was not completed. To be rescheduled once switch is wired.
|
INSP-Conference | 6/7/2016 | 6/7/2016 | 6/7/2016 | P | DONE |
Katie Marron
|
|
|
Called Anthony with Thorpe for a status update. The primary contractor is close to having all finishes done and then the final will be called in. System test has been previously completed.
|
INSP-Final | 3/28/2016 | 3/29/2016 | 3/29/2016 | P | PART |
Katie Marron
|
|
|
Unit 3590 Scope of work complete. Flow test completed satisfactory.
Unit 3594 still needs final test.
|
INSP-Final | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | CANC |
Troy Cobbley
|
|
|
Please call Anthony when you are headed out! Thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in | 1/26/2016 | 1/26/2016 | 1/26/2016 | P | DONE |
Katie Marron
|
|
|
Reinspected @ 4pm. Adjustments/additional insulation added. At time of inspection tenting ok.
Tenting inspection @ 1:30pm. Found a trouble spot in small bathroom. Called Anthony to adjust insulation.
|
INSP-Sprinkler Rough-in | 1/20/2016 | 1/21/2016 | 1/21/2016 | A | NR |
Katie Marron
|
|
|
Tenting was not complete at time of inspection (10:30 am). Was not able to reinspect, inspection needs to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 1/14/2016 | 1/15/2016 | 1/15/2016 | A | PASS |
Katie Marron
|
|
|
Unit 3590 - Tenting inspection Ok and revised approved plans on site. Roughin complete, Ok to cover all.
Unit 3594 needs tenting inspection.
|
INSP-Sprinkler Rough-in/Hydro | 1/8/2016 | 1/8/2016 | 1/8/2016 | P | PART |
Katie Marron
|
|
|
Rough-in inpection pass for #3594 and pending resubmittal approval for #3590.
Hydro static test completed satisfactory for both.
Still to be completed: backflow preventer and main valve. No tenting completed to date.
|