INSP-Final | 1/15/2016 | 1/15/2016 | 1/15/2016 | P | PASS |
Katie Marron
|
|
|
Last correction items completed. Scope of work complete. Permit finaled.
|
INSP-Final | 1/12/2016 | 1/13/2016 | 1/13/2016 | P | PART |
Katie Marron
|
|
|
Systems test completed satisfactory.
Final items to be completed. Eschuteons on heads in corridor currently being painted and sticker on outside alarm bell.
|
INSP-Sprinkler Rough-in/Hydro | 1/13/2016 | 1/13/2016 | 1/13/2016 | A | PASS |
Katie Marron
|
|
|
Hydrostatic retest completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 1/11/2016 | 1/12/2016 | 1/12/2016 | P | PART |
Katie Marron
|
|
|
Rough in fully complete. All perviously noted items completed satifactory.
Hydro Failed. Pressure dropped by 1-2 psi. Walked and found drip by upright sprinkler head in production bay. Hydro to be redone tomorrow in conjunction with final.
|
INSP-Sprinkler Rough-in | 1/6/2016 | 1/7/2016 | 1/7/2016 | A | PASS |
Katie Marron
|
|
|
Roughin complete. All hard lid areas OK to cover. Verified west stairwell and under stair areas.
Still to be completed, grid ceiling pendants (drops in place), uprights under cedar ceiling and dry sidewalls.
|
INSP-Sprinkler Rough-in | 12/29/2015 | 12/30/2015 | 12/30/2015 | A | PASS |
Katie Marron
|
|
|
Rough in completed satisfactory. Hard lids ok to cover except west stairwell. Pendants in grid ceiling and dry side walls still to be installed, see approved plans for circled heads. Mains/branchilnes were in place just missing drops and heads.
|
INSP-Supply line flush | 11/2/2015 | 11/2/2015 | 11/2/2015 | P | PASS |
Katie Marron
|
|
|
Supply line flush completed satisfactorily.
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2015 | 7/30/2015 | 7/30/2015 | A | PASS |
Jim Page
|
|
|
Underground hydrostatic test passed/complete
|
INSP-Sprinkler Rough-in | 7/1/2015 | 7/7/2015 | 7/7/2015 | A | PART |
Katie Marron
|
|
|
Underground 6" sprinkler supply pipe ok to cover.
|