INSP-Final | 12/30/2015 | 12/30/2015 | 12/30/2015 | P | PASS |
Katie Marron
|
|
|
Scope of work complete. Permit finaled. Flow test completed satisfactory. Verified pump house is heated and has a drain.
|
INSP-Final | 12/29/2015 | 12/29/2015 | 12/30/2015 | P | CANC |
Katie Marron
|
|
|
Per call with Anthony that system was not ready for inspection. Pump needed adjustments to provide enough pressure to trip flow switch.
|
INSP-Final | 12/10/2015 | 12/11/2015 | 12/11/2015 | A | FAIL |
Troy Cobbley
|
|
|
Something is wrong with the flow switch and the storage tank is not connected yet. Inspection stopped. Will need to re-schedule when ready and all items for final have been verified prior to scheduling another inspection.
|
INSP-Final | 12/7/2015 | 12/7/2015 | 12/7/2015 | P | CANC |
Troy Cobbley
|
|
|
No water yet
|
INSP-Final | 12/6/2015 | 12/7/2015 | 12/7/2015 | A | CANC |
Katie Marron
|
|
|
Please call Jake when you are on your way. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Final | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | CANC |
Jim Page
|
|
|
Inspection cancelled per conversation with Anthony, phone number ###-####, will reshedule inspection for later date.
|
INSP-Supply line flush | 11/2/2015 | 11/3/2015 | 11/2/2015 | A | PASS |
Katie Marron
|
|
|
Contractor excavated trench more so that no berm as previously agreed upon would be required. Depth of cover is good, ok to cover.
Pump house has walls, rooft and door. No floor drain as required is installed. Mentioned to Anthony.
|
INSP-Supply line flush | 10/30/2015 | 10/30/2015 | 10/30/2015 | P | CANC |
Thomas Walsh
|
|
|
Will call to reschedule on Monday. Ran out of time for this inspection, and Anthony said that he can wait till then.
|
INSP-Sprinkler Rough-in/Hydro | 10/5/2015 | 10/5/2015 | 10/6/2015 | P | PASS |
Katie Marron
|
|
|
Hydrostatic test pass satisfactorily.
|
INSP-Sprinkler Rough-in | 10/1/2015 | 10/2/2015 | 10/2/2015 | A | PASS |
Katie Marron
|
|
|
Sprinkler rough in complete. Ok to cover. A couple missing heads (open drops) to complete and the bathroom upstairs needs the sprinkler relocated to get as far away from light fixture as possible.
|
INSP-Supply line flush | 10/1/2015 | 10/1/2015 | 10/1/2015 | P | DONE |
Katie Marron
|
|
|
No flush, underground cover inspection. Depth is good until land slopes down to the pump house. Contractor verified that Owner ok to berm up ground there to reach appropriate cover, verify 6"-1' berm at final.
|