INSP-Final | 2/4/2016 | 2/4/2016 | 2/4/2016 | P | PASS |
Katie Marron
|
|
|
System test completed satisfactoy. Scope of work complete. Permit Finaled.
|
INSP-Sprinkler Rough-in/Hydro | 12/7/2015 | 12/7/2015 | 12/7/2015 | P | PASS |
Katie Marron
|
|
|
Hydrostatic test completed satisfactory (reading at 2:10pm 212 psi, again at 4:14pm 212psi) Rough in inspection completed satisfactory, ok to cover. **To be verified at final** two dry pendants in cooler, 4 dry sidewalls at entrances and one regular sidewall in electrical room. Stubs were present at roughin
|
INSP-Supply line flush | 12/7/2015 | 12/7/2015 | 12/7/2015 | A | DONE |
Katie Marron
|
|
|
Undergound supply line flush completed ok. Flushed for 3.5 minutes no significant debris.
|
INSP-Sprinkler Rough-in/Hydro | 11/30/2015 | 12/1/2015 | 12/1/2015 | A | CANC |
Katie Marron
|
|
|
Per phone call with Clarence. No heat is currently installed and temperatures do not allow for hydro.
|
INSP-Sprinkler Rough-in | 11/24/2015 | 11/30/2015 | 11/30/2015 | P | CANC |
Katie Marron
|
|
|
Call prior to going Phone #: 2088717472 >> Inspection requested via mobile web by Clarence Inspection cancelled via mobile web on Monday, November 30, 2015.
|
INSP-Sprinkler Rough-in | 11/17/2015 | 11/17/2015 | 11/17/2015 | P | DONE |
Katie Marron
|
|
|
Completed. See previous entry note.
|
INSP-Sprinkler Rough-in | 11/17/2015 | 11/17/2015 | 11/17/2015 | A | DONE |
Katie Marron
|
|
|
Completed underground supply inspection. Verified depth and thrust blocks. Underground OK to cover.
|
INSP-Sprinkler Rough-in | 11/17/2015 | 11/17/2015 | 11/17/2015 | P | DONE |
Katie Marron
|
|
|
Early Start Inspection on 11/3 for riser stub in. Riser ok to pour floor slab, discussed pouring around a ring for seismic protection. Verified appropriate depth on stub outside of building footing. End of pipe submerged in dirt, unsure if capped, ensure flush is done well at later date.
Initially posted to NAF15-00025 which is alarm permit. Added here to ensure documented appropriately.
|
INSP-Sprinkler Rough-in | 11/13/2015 | 11/16/2015 | 11/16/2015 | P | PART |
Katie Marron
|
|
|
Delay in hot taping at street water main connection prevented full underground inspection from happening. Water company on site at time of inspection. Mechanical tee at tap inspected, OK to cover.
|