INSP-Final | 5/18/2017 | 5/19/2017 | 5/19/2017 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 8/16/2016 | 8/16/2016 | 8/16/2016 | A | DONE |
Katie Marron
|
|
|
Remainder of UDG from sidewalk to riser was inspected and thrust blocks were observed being poured on 6/22/16. Note was added to wrong case.
|
INSP-Supply line flush | 8/11/2016 | 8/12/2016 | 8/12/2016 | P | PASS |
Katie Marron
|
|
|
Flush completed satisfactory
|
INSP-Sprinkler Rough-in/Hydro | 6/21/2016 | 6/22/2016 | 6/22/2016 | P | PASS |
Katie Marron
|
|
|
Hydro static test completed satisfactory. Only flush remains.
|
INSP-Supply line flush | 6/21/2016 | 6/22/2016 | 6/22/2016 | P | CANC |
Katie Marron
|
|
|
Flush after hydro Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | PART |
Troy Cobbley
|
|
|
Underground supply line is ok to cover from tap to the sidewalk.
|
INSP-Sprinkler Rough-in | 1/5/2016 | 1/6/2016 | 1/5/2016 | A | PART |
Troy Cobbley
|
|
|
Underground ok to cover up to sidewalk
|