INSP-Final | 9/29/2016 | 9/29/2016 | 9/29/2016 | P | PASS |
Katie Marron
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 9/29/2016 | 9/29/2016 | 9/29/2016 | P | PASS |
Katie Marron
|
|
|
Scope of work complete. Permit Finaled.
|
INSP-Supply line flush | 5/11/2016 | 5/12/2016 | 5/12/2016 | P | PASS |
Katie Marron
|
|
|
Underground flush completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | PASS |
Katie Marron
|
|
|
Underground hydro completed satisfactory.
|
INSP-Sprinkler Rough-in | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for underground supply main, underground approved for cover.
|
INSP-Sprinkler Rough-in | 3/29/2016 | 3/30/2016 | 3/30/2016 | P | NR |
Katie Marron
|
|
|
Under ground cover not ready, rescheduled for next day.
|
INSP-Sprinkler Rough-in | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | PART |
Troy Cobbley
|
|
|
Underground supply line is ok to cover from tap to the sidewalk.
|
INSP-Sprinkler Rough-in/Hydro | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | PART |
Troy Cobbley
|
|
|
Underground supply line is ok to cover from tap to the sidewalk.
|
INSP-Sprinkler Rough-in | 12/31/2015 | 1/5/2016 | 1/5/2016 | P | FAIL |
Troy Cobbley
|
|
|
Minumum 4'6" bury dept not met.
|