INSP-Final | 5/20/2016 | 5/23/2016 | 5/23/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 4/27/2016 | 4/27/2016 | 4/27/2016 | P | PASS |
Katie Marron
|
|
|
Underground flush completed satisfactorily.
|
INSP-Sprinkler Rough-in/Hydro | 4/26/2016 | 4/26/2016 | 4/26/2016 | P | PASS |
Katie Marron
|
|
|
Underground hydro completed satisfactorily.
|
INSP-Sprinkler Rough-in | 1/14/2016 | 1/14/2016 | 1/14/2016 | A | DONE |
Katie Marron
|
|
|
Inspected remaining underground line. From 90 under driveway to the T-Tap. Ok to cover. Inspection was completed on 1/13/16.
|
INSP-Sprinkler Rough-in/Hydro | 1/12/2016 | 1/12/2016 | 1/12/2016 | P | PART |
Katie Marron
|
|
|
Undergound cover for run of pipe from riser with thrust block, to just before it turns parallel to street completed satisfactory.
90 degree bend & thrust block, pipe under driveway, and tap to main still be completed.
|