INSP-Final | 4/17/2017 | 4/18/2017 | 4/18/2017 | P | PASS |
Jim Page
|
|
|
Previously noted items have been repaired, sprinkler heads next to registers on level 3 will be changed to an intermediate temperature head (sprinkler heads are less than 24 inches away from heat register). Final fire sprinkler passed/complete
|
INSP-Final | 4/13/2017 | 4/14/2017 | 4/14/2017 | P | FAIL |
Scott Arellano
|
|
|
Hallway Sprinkler heads obstructed by ceiling light fixture at multiple units. Sprinkler heads need to be relocated to 36 inches from fixture or fixtures need to be replaced with recessed lighting.
|
INSP-Sprinkler Rough-in | 12/14/2016 | 12/14/2016 | 12/14/2016 | P | DONE |
Katie Marron
|
|
|
At time of inspection tenting completed satisfactory. One uncovered spot identified, insulators on site to correct.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2016 | 12/13/2016 | 12/13/2016 | A | PASS |
Katie Marron
|
|
|
All three system satisfactorily hydro tested. Roughin third floor completed. Heat tape has been installed.
-Tenting was not complete and will need to be reinspected. No dry sidewalls installed yet
|
INSP-Sprinkler Rough-in | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PART |
Katie Marron
|
|
|
Rough-in completed satisfactory for 1st and 2nd floors.
Sidewalls and 3rd floor w/tenting still to be completed.
|