INSP-Final | 6/16/2016 | 6/16/2016 | 6/16/2016 | P | PASS |
Katie Marron
|
|
|
Scope of work complete. Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 4/5/2016 | 4/6/2016 | 4/6/2016 | A | DONE |
Katie Marron
|
|
|
Verified six uprights have been added along the south wall.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2016 | 4/5/2016 | 4/5/2016 | P | CANC |
Katie Marron
|
|
|
Spoke with Bruce in the morning he was going to call when work was complete/ready for inspection. Called at 1pm and did not reach him. Inspection cancelled.
|
INSP-Sprinkler Rough-in | 3/31/2016 | 4/4/2016 | 4/4/2016 | A | FAIL |
Troy Cobbley
|
|
|
Existing upright sprinkler coverage along the south wall, over the restrooms/office are overspaced off of the wall. I measure them at 8'-4". Part of the sprinkles pendants have been covered prior to inspection. I posted a "do not cover" sticker on the window.
|