INSP-Final | 1/26/2017 | 1/26/2017 | 1/26/2017 | P | PASS |
Katie Marron
|
|
|
System is now monitored and active. Scope of work complete. Permit Finaled.
|
INSP-Final | 1/24/2017 | 1/25/2017 | 1/25/2017 | A | PART |
Katie Marron
|
|
|
Operation test completed (flow test w/outside bell, tampers reporting to panel, forward flow). Fire Alarm contractor could not be present, so no monitoring capability. System was not left in active status.
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2017 | 1/25/2017 | 1/25/2017 | A | PASS |
Katie Marron
|
|
|
Hydrostatic test for overhead and racking completed satisfactory.
|
INSP-Final | 1/18/2017 | 1/20/2017 | 1/20/2017 | A | NR |
Katie Marron
|
|
|
Not ready per phone call with contractor
|
INSP-Sprinkler Rough-in/Hydro | 1/18/2017 | 1/18/2017 | 1/18/2017 | P | PART |
Katie Marron
|
|
|
Rough-in completed satisfactorily. Hydro static test passed on underground. Underground flush completed.
Hydro static tests failed on rack and over head systems, shall need to be redone.
|
INSP-Sprinkler Rough-in/Hydro | 1/18/2017 | 1/20/2017 | 1/18/2017 | P | CANC |
Troy Cobbley
|
|
|
Call prior to going Phone #: 8017063435 >> Inspection requested via mobile web by Dan snith Inspection cancelled via mobile web on Wednesday, January 18, 2017.
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2017 | 1/18/2017 | 1/18/2017 | A | CANC |
Katie Marron
|
|
|
Call prior to going Phone #: 8017063435 >> Inspection requested via mobile web by Dan smith Inspection cancelled via mobile web on Wednesday, January 18, 2017.
|
INSP-Sprinkler Rough-in | 8/24/2016 | 8/25/2016 | 8/25/2016 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover.
|
INSP-Conference | 8/24/2016 | 8/24/2016 | 8/24/2016 | P | DONE |
Troy Cobbley
|
|
|
Went over underground supply bury requirements.
|