INSP-Final | 12/6/2016 | 12/7/2016 | 12/7/2016 | A | PASS |
Katie Marron
|
|
|
Systems acceptance tests completed OK. Scope of work complete. Permit Finaled.
|
INSP-Final | 11/28/2016 | 11/29/2016 | 11/29/2016 | A | CANC |
Katie Marron
|
|
|
Fire Alarm Finial - Scott Carter will be contact Plans are to final with Protex on 11/29/16 @ 8AM. Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Supply line flush | 11/8/2016 | 11/9/2016 | 11/9/2016 | P | DONE |
Katie Marron
|
|
|
Supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in | 9/23/2016 | 9/26/2016 | 9/26/2016 | A | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok for cover. Tim/scott approved the piping needing to meet the 4'6" dept of cover with-in 20' of connection point.
|
INSP-Sprinkler Rough-in/Hydro | 9/21/2016 | 9/22/2016 | 9/22/2016 | A | FAIL |
Troy Cobbley
|
|
|
Piping is not buried deep enough. It varies from 4'-2" to 4'-0". Minimum bury depth is 4'-6"
|
INSP-Sprinkler Rough-in | 9/16/2016 | 9/16/2016 | 9/16/2016 | P | FAIL |
Katie Marron
|
|
|
From stub up to ~15' from building. Minimum ground coverage (4'-6") not acheived. Pipe has approx. 3'-6". Not approved for cover.
|