INSP-Final | 6/29/2017 | 6/30/2017 | 6/30/2017 | A | DONE |
Troy Cobbley
|
|
|
Call prior to going Phone #: 9957215 >> Inspection requested via mobile web by Lonnie
|
DOC - Permit Finaled | | | 6/30/2017 | | DONE |
Troy Cobbley
|
|
|
as per Troy doc final-won't let him do it in the field
|
INSP-Final | 6/26/2017 | 6/27/2017 | 6/27/2017 | A | CANC |
Troy Cobbley
|
|
|
The fire alarm contractor is not ready for testing yet
|
INSP-Sprinkler Rough-in/Hydro | 5/17/2017 | 5/17/2017 | 5/17/2017 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test for the dry system passed
|
INSP-Sprinkler Rough-in/Hydro | 5/15/2017 | 5/16/2017 | 5/16/2017 | A | PART |
Scott Arellano
|
|
|
Rough toc cover PASS. Crawl space and overhead inspected. Overbuild sprinklers to be heated with active heating through transfer grills from warehouse and lower office combined with insulation tenting. Finish sheet rock needs to be installed prior to final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 4/28/2017 | 5/1/2017 | 5/1/2017 | A | PASS |
Jim Page
|
|
|
Tenting inspection complete, overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in | 4/25/2017 | 4/25/2017 | 4/25/2017 | P | PART |
Jim Page
|
|
|
Previously noted items for sway brace attachment corrected/completed, tenting/sway brace attachments approved for cover west of the fireplace, tenting still needs to be installed over the 6 inch supply main, main supply cannot be covered until tenting is inspected/passed.
|
INSP-Sprinkler Rough-in | 4/20/2017 | 4/20/2017 | 4/20/2017 | P | PASS |
Troy Cobbley
|
|
|
Did not make contact with Lonnie but met with the job superintendant Nacho. I gave approval for the piping in the Commons Area to be covered. Tenting in this area passed. I noted that the earth quake bracing needs to utilize through bolts at all connection points, not lag bolts. I discussed this with Nacho and he was going to let Lonnie know.
|
INSP-Sprinkler Rough-in/Hydro | 4/12/2017 | 4/13/2017 | 4/13/2017 | A | PASS |
Scott Arellano
|
|
|
2 hour hydro static test witnessed on wet system at West Wing.
|
INSP-Sprinkler Rough-in | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | PART |
Scott Arellano
|
|
|
Tenting Inspection on West wing wet system complete.
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2017 | 3/30/2017 | 3/30/2017 | P | PART |
Katie Marron
|
|
|
Tenting for south wing. At time of inspection tenting ok. Verified missing baffles for dry system were installed.
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2017 | 3/29/2017 | 3/29/2017 | P | PART |
Katie Marron
|
|
|
Rough-in completed on remaining wet and dry system. *Straps missing on 4" wet in common space *Verified missing drop corrected from previous inspection.
|
INSP-Sprinkler Rough-in | 3/16/2017 | 3/16/2017 | 3/16/2017 | A | PART |
Katie Marron
|
|
|
Completed rough-in on wet and dry system for south wing up to common area (see site plans). *One drop in hallway missing to be verified at tenting inspection.* *Baffles required for dry system to be verified at tenting* *Eaves are currently open to rest of ceiling space as indicated in plan review response for item 2*
|