INSP-Final | 7/31/2018 | 8/1/2018 | 8/1/2018 | A | DONE |
Troy Cobbley
|
|
|
Permit finaled
|
DOC - Permit Finaled | | | 8/1/2018 | | DONE |
|
|
|
Per Troy Cobbley
|
INSP-Sprinkler Rough-in/Hydro | 7/18/2018 | 7/19/2018 | 7/19/2018 | P | PASS |
Troy Cobbley
|
|
|
Third floor hydro test and third floor rough-in passed. Piping can be covered.
RUDY IS OUR FOREMAN ON THIS PROJECT Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 7/10/2018 | 7/11/2018 | 7/11/2018 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro tests of the first and second floors passed. Rough-in passed for the first and second floors and piping can be covered.
RICK FRY IS OUR CONTACT PERSON. Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PASS |
Troy Cobbley
|
|
|
The piping above the hardlids on the 3rd floor is ok for cover. I also did a preliminary rough-in inspection for all floors. Everything appears ok except for a few items which include branchline restraints will be required for the second floor/south side branchlines and an access panel is needed for the ball drip. Another rough-in inspection will be needed for a cover inspection once the sprinkler drops have been cut.
RICK FRY IS OUR CONTACT Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for piping above the hard lids that has been approved for cover.
RICK FRY IS OUR CONTACT Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 5/24/2018 | 5/25/2018 | 5/25/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping located above hardlids, notated cicty approved drawings areas approved for cover.
RICK FRY IS OUR CONTACT Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 5/18/2018 | 5/21/2018 | 5/21/2018 | A | PASS |
Troy Cobbley
|
|
|
The two pendant heads in the first floor west entry are ok for cover.
|
INSP-Sprinkler Rough-in | 5/9/2018 | 5/10/2018 | 5/10/2018 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the areas on the first floor, marked "ok" where piping can be covered.
|