Permit Information
Permit NumberPLM00-02912
StatusFinaled
Name RM MECHANICAL
Site Address 8000 S FEDERAL WAY
Project NameMIC #36-PC 3157
Customer Number 
ePlanReview 
Description
8/16/00//MICRON TECHNOLOGY/BLDG #36/SECTION B,C, & D/SHELL ONLY/UNDERGROUND SEWER, DWV UNDERPASSED STEM DRAIN SYSTEM SECTION/INITIAL CERT OF VALUE $65,000/MLS
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final11/6/200111/6/200111/6/2001APART
DetailsBill VanDegrift
Added by Inspector: 330 On 11/6/2001 11:58:10 AM set all equipment
Plumbing Rough-in6/18/20016/19/20016/19/2001APART
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 06/18/2001 at 13:21:09. Contact: ###-####. interceptors 6/19/2001 2:06:07 PM
Plumbing Rough-in5/18/20015/18/20015/18/2001PPART
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 05/18/2001 at 07:36:18. Contact: ###-####. last of the kitchen w&v gw 5/18/2001 3:20:24 PM
Plumbing Rough-in5/16/20015/16/20015/16/2001PPART
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 05/16/2001 at 07:45:30. Contact: ###-####. part gw kitchen islands 5/16/2001 3:41:23 PM
Groundwork5/4/20015/4/20015/4/2001PPART
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 05/04/2001 at 09:58:41. Contact: ###-####. floor sink, rd stub out east side by foundation wall test ok 5/4/2001 3:56:15 PM
Plumbing Rough-in3/12/20013/12/20013/12/2001PPART
DetailsBill VanDegrift
###-#### partial gw in kitchen ok 3/12/2001 3:27:36 PM col. 4.75-3 3/12/2001 3:41:30 PM
Groundwork3/9/20013/9/20013/9/2001PNR
DetailsBill VanDegrift
###-#### WASTE VENT UNDERGROUND
Plumbing Rough-in3/1/20013/2/20013/2/2001APART
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 03/01/2001 at 15:58:32. Contact: ###-####. 50' of 4" waste from main to north fire riser room. 3/2/2001 11:04:53 AM
Plumbing Rough-in2/14/20012/14/20012/14/2001PCANC
DetailsBill VanDegrift
###-####
Plumbing Rough-in2/14/20012/14/20012/14/2001APART
DetailsJim Johnson
Scheduled by Inspector: 309 On 2/14/2001 10:17:54 AM RWL 8 inch at line 20-A . 20-L 16-A riser clamp to be installed when fire caulking is completed RWL 4 inch at line 21-D ok 2/14/2001 3:00:08 PM
Groundwork10/25/200010/25/200010/25/2000APART
DetailsBill VanDegrift
Added by Inspector: 330 On 10/25/2000 partial kitchen gw ok
Plumbing Rough-in10/17/200010/17/200010/17/2000PPART
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 10/17/2000 at 09:13:00. Contact: ###-####. more kitchen gw 10/18/2000 7:38:33 AM
Plumbing Rough-in10/11/200010/12/200010/12/2000APART
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 10/11/2000 at 15:39:34. Contact: ###-####. restroom group area 3 gw ok 10/12/2000 3:44:56 PM
Plumbing Rough-in10/2/200010/2/200010/2/2000APART
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 10/02/2000 at 07:21:54. Contact: ###-####. partial gw ok kitchen area 10/2/2000 6:08:59 PM
Plumbing Rough-in9/14/20009/15/20009/15/2000APART
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 09/14/2000 at 15:40:58. Contact: ###-####. part gw floor sink in first fire riser room 9/15/2000 3:22:53 PM
Groundwork8/29/20008/29/20008/29/2000PPART
DetailsBill VanDegrift
Added by Inspector: 330 On 8/29/2000